The Bartram, LLC v. C.B. Contractors

November 22, 2011

THE BARTRAM, LLC, PLAINTIFF,
v.
C.B. CONTRACTORS, LLC. ET AL., DEFENDANTS.
C.B. CONTRACTORS, LLC, DEFENDANT/THIRD-PARTY PLAINTIFF,
v.
DUFFIELD ALUMINUM D/B/A DHI ROOFING, ET AL., THIRD-PARTY DEFENDANTS.
LOWRY CONSTRUCTION & FRAMING, INC., THIRD-PARTY DEFENDANT/FOURTH-PARTY PLAINTIFF,
v.
CMG SIDING, INC., ET AL., FOURTH-PARTY DEFENDANTS.



The opinion of the court was delivered by: Stephan P. Mickle Senior United States District Judge

ORDER ON MEDIATION OF THIRD AND FOURTH PARTY CLAIMS

This cause comes before the Court on Defendant, C.B. Contractors, LLC's Motion to Extend the Court Ordered Mediation Deadline and Motion to Compel Mediation (doc. 343) and the response filed by Dai-Cole Waterproofing, Inc. (doc. 354).

Given the number of parties involved in this case and the complexities of the mediation process, the Court finds that personal attendance of the parties, along with their trial counsel and designated corporate and insurance claims representatives, is necessary. Accordingly, it is ORDERED AND ADJUDGED:

1. C.B. Contractors, LLC's motion (doc. 343) is granted.

2. The parties shall have up to and including January 31, 2012, to complete mediation of the Third and Fourth party claims.

3. The parties, along with their trial counsel and designated corporate and insurance claims representatives, must appear in person.

Stephan P. Mickle

20111122

© 1992-2011 VersusLaw ...

Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.